HAUSE SEWER NETWORKsewers@hause.ca403-679-3100
SewerInstall.com
Testing guide

Sewer line inspection and testing: what happens before backfill

How a new sewer is tested and inspected in Alberta: the water, air, final and ball tests in the plumbing code, Calgary's pre-backfill inspection, common fails.

A conceptual open sewer installation with removable test caps, a standpipe and camera equipment, illustrating the checks performed before an inspected pipe is covered with backfill.
Inspect & Test / field studySewer line inspection and testing: what happens before backfillConceptual illustration, not to scale or a site assessment.Read the guide
Short answer

A new sewer line is tested and inspected while the trench is still open. The National Plumbing Code of Canada 2020 requires a water test holding at least a 3 m column on all joints for 15 minutes, or an air test holding 35 kPa for at least 15 minutes, before piping is covered, with a ball test on request. Calgary then inspects sanitary services at the pre-backfill stage.

Key takeaways
  • Water test: at least a 3 m water column on all joints, kept full for 15 minutes (NPC 2.3.6.4).
  • Air test: 35 kPa held at least 15 minutes without a drop, following the pipe maker's instructions (NPC 2.3.6.5).
  • Ball test: a dense ball rolled through the pipe, when the authority requests it (NPC 2.3.6.7).
  • Calgary generates sanitary and storm inspections at the pre-backfill stage; do not cover pipe before sign-off.
A sewer camera reel, monitor and locator on a front lawn in autumn
IllustrationA push-camera reel and monitor with the locator receiver, set up on a front lawn.
Test methods for new drain and sewer pipingFour ways new piping is proved. A water test fills the section and holds a water column at least 3 metres above the joints for 15 minutes. An air test pressurises the plugged section to 35 kilopascals and holds it for at least 15 minutes without a drop. A ball test rolls a dense ball through the pipe to prove it is clear and continuous. A recorded camera run is common practice and shows grade and joints, but it is not one of the code tests. 3 mWATER TEST≥3 m column on all jointsheld 15 min 35 kPaAIR TEST35 kPa, no dropheld at least 15 min BALL TESTa dense ball rolled throughproves it is clear 12.4 mCAMERA RECORDcommon practice,not a code test NPC 2020 · 2.3.6.4 WATER · 2.3.6.5 AIR · 2.3.6.7 BALL · TEST BEFORE THE PIPE IS COVERED Air testing plastic pipe is only done where the pipe maker's instructions allow it.
Fig. 1How a new drain or sewer is proved before it is buried: water column test, air test, ball test, and a recorded camera run.

01 /Why is a sewer tested before it is buried?

Because it is the last moment anyone can see it. Once the trench is backfilled, a leaking joint, a pipe out of grade or a missing cleanout can only be found with a camera and fixed with an excavator. The plumbing code builds the timing into the rule: Article 2.3.6.1 says that after a section of a drainage or venting system has been roughed in, and before any fixture is installed or piping is covered, a water pressure test or an air pressure test shall be conducted. The inspection that follows is the authority's check that the work, and the test, meet the code.

Testing protects everyone. The owner gets a line that is proven tight and continuous. The installer gets a clean record that the work was right on the day it was covered. The municipality gets assurance that groundwater is not leaking into the sanitary system and sewage is not leaking out. A contractor who suggests skipping the test to save a day is suggesting you accept an unproven pipe.

02 /What tests does the plumbing code set out?

Four, in Subsection 2.3.6 of the National Plumbing Code of Canada 2020, which Alberta enforces without changes. The code says drainage pipes must be capable of withstanding the water, air and final tests without leakage, and of meeting a ball test (Article 2.3.6.2).

Test methods for drainage systems, NPC 2020 Subsection 2.3.6
TestHow it worksPass conditionWhen
Water pressure test (2.3.6.4)Every opening except the highest is plugged or capped; the section is filled so there is a water column of at least 3 m on all jointsKept filled for 15 min without leakageAfter rough-in, before covering; this or the air test
Air pressure test (2.3.6.5)Air is forced into the plugged section, following the maker's instructions for the pipe35 kPa held at least 15 min without a dropAfter rough-in, before covering; this or the water test
Final test (2.3.6.6)Traps filled; smoke forced in, roof terminals closed when smoke appears, or air alone25 mm water column held 15 min without adding smoke or airAfter fixtures are installed, when requested
Ball test (2.3.6.7)A hard ball dense enough not to float is rolled through the pipeThe ball passesWhen requested
Test methods for new drain and sewer pipingFour ways new piping is proved. A water test fills the section and holds a water column at least 3 metres above the joints for 15 minutes. An air test pressurises the plugged section to 35 kilopascals and holds it for at least 15 minutes without a drop. A ball test rolls a dense ball through the pipe to prove it is clear and continuous. A recorded camera run is common practice and shows grade and joints, but it is not one of the code tests. 3 mWATER TEST≥3 m column on all jointsheld 15 min 35 kPaAIR TEST35 kPa, no dropheld at least 15 min BALL TESTa dense ball rolled throughproves it is clear 12.4 mCAMERA RECORDcommon practice,not a code test NPC 2020 · 2.3.6.4 WATER · 2.3.6.5 AIR · 2.3.6.7 BALL · TEST BEFORE THE PIPE IS COVERED Air testing plastic pipe is only done where the pipe maker's instructions allow it.
Fig. 2Water column, air gauge and ball: the code tests. A camera run is common practice alongside them but is not one of the code tests.

03 /How is a water test done on a sewer?

By plugging the downstream end and filling the pipe until water stands high enough to put at least 3 m of head on every joint. On a building sewer, that usually means a test plug at the far end and a standpipe or the building's own riser at the high end, filled until the level is 3 m above the joints being tested. The section stays filled for 15 minutes, and the level must hold. Any drop means a leak, which is then found by looking along the open trench for water at the joints.

A long sewer on a steep grade can be hard to test in one piece, because 3 m of head at the top can be much more at the bottom. Installers test in sections in that case, with plugs between. A water test is not a good idea in freezing weather unless the water is drained promptly; in winter, the air test is often preferred where the pipe maker allows it.

04 /When is an air test used, and what are the risks?

An air test is used where water is impractical: cold weather, long sections or where filling and draining would be messy. The code says air tests shall be conducted in accordance with the manufacturer's instructions for each piping material, with air forced in until the pressure reaches 35 kPa and held for at least 15 minutes without a drop. Its explanatory note adds that a non-toxic indicating substance such as an aerosol, fluorescent dye, smoke or odorant may help find a leak, as long as it is compatible with the pipe and does not affect the result.

A test plug that slips under pressure is also a hazard. Plugs are rated for a pressure and pipe size; using the wrong one, or one not fully seated, is how plugs are launched out of pipes. None of this is exotic, but it is why a test is done carefully and not rushed at the end of a long day.

Sewer camera view down a clean white ABS plastic pipe
IllustrationCamera view of a sound ABS plastic line: smooth walls, water running along the bottom, nothing to report.

05 /What does the inspector check in the open trench?

The inspector checks that the installation matches the code and the permit, and that the test has been done or is done in front of them. In Calgary, sanitary and storm inspections are generated automatically at the pre-backfill stage, and inspection requests for the following day are due by 2 p.m. through 311 or an online account. Around Calgary the process differs in detail: Cochrane's homeowner guide describes a groundworks rough-in and a mandatory final, Foothills County requires a rough-in of drain, waste and vent piping below the slab to outside the building, and Chestermere asks for 2 to 3 business days' notice.

What a pre-backfill inspection typically looks at
ItemWhat the inspector wants to see
Pipe and fittingsMaterial and markings meeting a listed standard; wyes, not tees; no saddle hubs
SizeAt least 4 inch for a building sewer connected to a public sewer
GradeAt least the minimum for the size, steady, no dips
SupportFirm, continuous bedding; no blocks or stones under the pipe
CleanoutsMain cleanout near the building and spacing and bend rules met
Backflow protectionBackwater valve where the authority requires one
CoverDepth consistent with the local frost rule
TestWater or air test holding

Calgary's quick trench program for new single and semi-detached homes lets qualified contractors document a trench with photographs, uploaded before backfill, showing site location, pipe size and material, backfill material and location markings. Even where that program applies, the record has to exist before the trench is closed.

06 /Why do sewer lines fail inspection?

Usually for one of a short list of reasons, most of which are cheap to fix before backfill and expensive after.

  • The test does not hold: a gasket not fully home, a solvent joint not seated, a coupling band loose, or a test plug leaking.
  • Grade problems: a section flatter than the minimum, a dip over a soft spot, or a change of slope between cleanouts.
  • Wrong fittings: a tee or a short elbow where a wye or long bend is required, or a saddle tap into an existing pipe.
  • Missing or misplaced cleanouts: no cleanout near the building, or bends beyond the allowance without one.
  • Bedding and support: pipe on rocks or blocks, or no bedding under part of the run.
  • Paperwork: no permit posted, or work covered before the inspection was booked.

A failed inspection is not a disaster if the trench is still open: the item is corrected and the inspector returns. It becomes costly when the work was covered first. The laying sequence that avoids most of these is in how a sewer line is installed, and the bedding rules are in bedding and backfill.

07 /Should you also get a camera record of the new line?

It is worth asking for. A camera run after laying, and ideally after backfill, shows the grade, every joint and the connection, and gives the owner a video baseline for the life of the pipe. It can catch a joint displaced by backfilling or a section that settled, which the pre-backfill test cannot, because it happens after. It is not one of the code tests and does not replace them; it complements them. Sister-site planning ranges put a post-work camera video at $0 to $400 when included in a job.

Keep the test record, the inspection sign-off and the video together with the permit. For the full job order, see the installation process; for what a camera inspection of an older line involves, SewerInspector.ca covers report codes and defect reading. When you are ready to plan, send the details.

FAQQuestions people ask

How long does a sewer water test last?

The section is kept filled with at least a 3 m water column on the joints for 15 minutes under NPC 2020 Article 2.3.6.4.

What pressure is used for a sewer air test?

35 kPa, held for at least 15 minutes without a drop, following the pipe maker's instructions (NPC 2020 Article 2.3.6.5).

What is a ball test on a drain?

A hard ball dense enough not to float is rolled through the pipe to show it is clear and continuous. The authority can request it.

Can I backfill my sewer before the inspection?

No. Calgary generates the sanitary inspection at the pre-backfill stage, and covering the pipe first usually means exposing it again.

Is a camera inspection required for a new sewer?

Not by the plumbing code, which relies on water, air and ball tests. A camera record is still a sensible addition for the owner's file.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.